Option B - Playspace & Skate/Learn to Ride Track

27 May 2025

At the Wednesday 19 February 2025 Ordinary Meeting of Council it was resolved that:

  1. Council proceed with the Concept Design Option B for the Colo Vale Railway Park in response to the community consultation outcomes and site-based constraints.
  2. That the Jurd Park Masterplan be reviewed to identify suitable location for inclusion of a modest pump track and skate facility, with construction to them be delivered through future funding opportunities.

Following community consultation in late 2024, Moduplay has been awarded the contract to build the Option B design (playspace and skate/learn to ride track).

With landowner approval secured by Transport Asset Manager (TAM), construction is anticipated to begin in late May 2025. Vegetation has started to be cleared from the site in preparation for these works, and we are aiming for the new park to open in August, subject to weather conditions.